Flagship Auckland Social Housing Already 78 Per Cent Behind Schedule

New Zealand First says National-led government’s flagship Auckland social housing build programme is already massively behind schedule just 18-days into it.

“Amy Adams is nothing more than Nick Smith in a dress,” says New Zealand First Leader and Member of Parliament for Northland, Rt Hon Winston Peters.

“Minister Adams boldly announced in May that, ‘12,421 new houses will be built across 41 suburbs’ in Auckland and ‘that works out to be on average roughly 11 houses built every day’.

“In the first 18-days of this financial year did we find 198 completed houses? Not likely.  There were just 43 completions so instead of ‘around 11 houses a day’ it was just two and at that rate, just 2,608 houses will be built over the next three years and not 12,421.

“Being 78 per cent behind schedule has National written all over it because it’s fallen into the trap of ‘targets’ and ‘re-announcements.’ Yet its real people who are suffering from National’s empty promises and lack of delivery.   

“It is some two and a half years since Nick Smith first said, ‘land for 34,000 houses; more land has been opened up in Auckland in the last 12 months than in the last 10 years’.  Two and a half years on and Minister Adams has the same housing target and is proving just as unsuccessful.

“We were always suspicious of this target because in all of 2015, Auckland Council only issued 5,016 Code Compliance Certificates for all houses across the entire city. 

“National will never get on top of housing while it obsesses over employing pen-pushers, lawyers and accountants.  That’s why New Zealand First’s focus is on tradies and architects instead,” says Mr Peters.

Mr Peters Question: In each day since 1 July 2017, how many houses have been built in Auckland, if any, to meet her commitment to deliver the first stage of 34,000 new homes to be built over the next 10 years?

Portfolio:                      Social Housing

Minister:                      Hon Amy Adams

Date Lodged:              18/07/2017

Date Answered:          26/07/2017

Minister’s Answer: I have been advised 43 properties have been completed in Auckland as part of the Crown Building Project from 1 July 2017 to 18 July 2017.